Iranian and Russian officials oversaw pre-commissioning tests at Bushehr, a visible step toward bringing Iran’s Russian-assisted nuclear power plant into operation.
Log in om dit verhaal leuk te vinden of te bookmarken.
🔖 Bookmarken
Nu in het nieuws
Nog geen afbeeldingen of video's voor deze gebeurtenis.
Gerelateerde evenementen
What did the February 2009 Bushehr tests mark?
🎉😄
😢
Uitleg
Iranian and Russian officials oversaw pre-commissioning tests at Bushehr, a visible step toward bringing Iran’s Russian-assisted nuclear power plant into operation.
The February 2009 Bushehr test itself marked commercial electricity generation.
🎉😄
😢
Uitleg
This test used dummy fuel and checked plant systems. It did not mark commercial electricity generation or the inauguration already recorded in Batch 001.