Arak’s strategic junction of two 400-kilovolt north–south transmission lines reportedly suffered three wartime attacks: two caused severe damage and one minor damage. Service resumed after each, but much repair work remained temporary.
Log in om dit verhaal leuk te vinden of te bookmarken.
🔖 Bookmarken
Nog geen afbeeldingen of video's voor deze gebeurtenis.
Gerelateerde evenementen
Nog geen quizvragen voor dit verhaal.
Arak’s strategic grid junction reportedly resumed service after each of three wartime attacks.
🎉😄
😢
Uitleg
Arak’s strategic junction of two 400-kilovolt north–south transmission lines reportedly suffered three wartime attacks: two caused severe damage and one minor damage. Service resumed after each, but much repair work remained temporary.