Inspecting Ramine power station, experts saw a turbine still under repair and damaged parts in the yard. Loss of components had delayed both restoration of one generating unit and completion of two others.
Log in to like or bookmark this story.
๐ Bookmark
No images or videos for this event yet.
Related Events
No quiz questions for this story yet.
Loss of vital components delayed reconstruction and completion of generating units at Ramine.
๐๐
๐ข
Explanation
The mission saw damage and shortages affecting existing and unfinished generating units.